Thyssen Mining, Inc. AAI conducted a review of the tunnel design (completed by others) and recommended changes for Thyssen Mining (the construction contractor) whose corporate office is located [...]
As a subcontractor to PBESS, Agapito Associates, Inc. (Agapito) was responsible for geotechnical design and construction confirmation for the Jurong Rock Caverns, Jurong Island, Singapore. [...]
American Borate Company The Billie Mine utilized long-hole stoping with backfilling to extract borate. This mining method resulted in the creation of tall, narrow pillars which were critical to [...]
West Ridge Resources, Inc. (WRRI) commissioned Agapito Associates, Inc. (AAI) to analyze subsidence potential from planned longwall mining in the vicinity of the Grassy Trail reservoir adjacent [...]
AAI was contracted by Graymont to perform a study of alternative accesses from surface to the underground limestone mine at Pleasant Gap, Pennsylvania. The options included two declines through [...]
Order of Magnitude Studies and Geotechnical Characterization Order of Magnitude studies for conventional room-and-pillar mining, longwall mining, and solution mining of a potential soda ash mine [...]
Intrepid Potash LLC In 2008, 2009, and 2010, Agapito Associates, Inc. prepared a United States Security Exchange Commission compliant reserve estimate for all five potash operations for Intrepid [...]